Please be advised that bridge assessment work will take place during the week of September 9 to 13 on select municipal bridges. Engineers will be using rope access techniques and inspection trucks, and may be seen climbing or working above and below bridge decks to complete their assessments.
The following bridges are expected to have lane closures:
- First Avenue South Bridge
- Tuesday, September 10, from 7:30 to 11:30 a.m.
- Keewatin Channel Bridge
- Tuesday, September 10, from 1:00 to 6:00 p.m.
- Bay Street Overpass
- Wednesday, September 11, from 8:00 to 11:00 a.m.
- Cameron Bay Bridge
- Wednesday, September 11, from 12:00 to 6:00 p.m.
This is Phase 2 of the City’s Biennial Bridge Assessment Project which reports on the status of municipal bridges for maintenance planning.
Thank you for your attention to those working on the bridges.